Prior To Installation
The surface to be paved to be flat, and free from substance: Dust, impermeable products, soluble salts, and all those product which are incompatible with adhesive material. In case of crumbling of the base, it must be removed till getting a firm surface.
Laying
Spending on the surface using a dentate trowel, whose size will vary from 6x6 to 9x9 mm. Depending on the size and manufacturer’s instructions.
Leveling
Hit the tile with a rubber hammer (from the center to the edges of the tiles.) In order to distribute and level the tiles.
Spacing
Tiles must be paved leaving a gap between them which will vary from 1mm to 3mm. Joints fro placing them.
Joining
Joining has to be carried out using a rubber palette knife, which will be used to compress material with backwards and forwards movements. In this way Joints will be field to over-flowing. Anyhow please follow the manufacturer’s introduction in how to use the product – drying time, removing leftovers and cleaning.
After Laying
Once the work has been finished. There are leftovers of the employed materials which have to be removed as soon as possible (cement, joints material, etc…) for this, we recommended using a cement remover or any other acid based decaling product.